March 2012 |
Installation completion of Gyeongsangnam-do Changwon-si Jinhae-gu MSW incineration plant steam turbine generator(400Kw) |
September 2011 |
Commissioning, Operation & Maintenance work of Gyeonggi-do Paju-si MSW incineration plant(90ton/day) |
September 2009 |
Commissioning, Operation & Maintenance Work of Jeollabuk-do Iksan-si MSW incineration plant(200ton/day) |
January 2009 |
Commissioning, Operation & Maintenance Work of Jeollanam-do Haenam-gun MSW incineration plant(25ton/day)
Commissioning, Operation & Maintenance Work of Jeollanam-do Kangjin-gun MSW incineration plant(20ton/day) |
January 2006 |
Commissioning, Operation & Maintenance Work of Incheon Metro City Songdo MSW incineration plant(500ton/day) |
September 2005 |
Commissioning, Operation & Maintenance Work of Gyeongsangnam-do Changwon-si Jinhae-gu MSW incineration plant(50ton/day) |
April 2003 |
Commissioning, Operation & Maintenance Work of Jeju-do MSW incineration plant(200ton/day & 70ton/day) |
February 2000 |
Commissioning, Operation & Maintenance Work of Gyeonggi-do Bucheon-si MSW incineration plant(300ton/day) |
November 1998 |
Commissioning, Operation & Maintenance Work of Adegu Metro City MSW incineration plant(600ton/day) |
January 1997 |
Commissioning, Operation & Maintenance Work of Gyeonggi-do Bucheon-si Samjeong-dong MSW incineration plant(200ton/day) |
October 1996 |
Established Wooju Envitech Inc. |